Village of Beechy - Landfill Decommissioning
Federal contribution
$32,100
Federal share40%
of $80.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 26, 2024
20242025
Built
Approved 9 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Beechy
- Construction start
- Jul 30, 2024(actual)
- Construction end
- Jan 23, 2025(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 3, 2024
- Construction end3 weeks lateforecast Dec 31, 2024