Village of Beechy - Landfill Decommissioning

Beechy, Saskatchewan

completeSolid Waste ManagementGIS
Federal contribution
$32,100
Federal share40%

of $80.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 26, 2024
20242025
Built

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Beechy
Construction start
Jul 30, 2024(actual)
Construction end
Jan 23, 2025(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 3, 2024
  • Construction end3 weeks lateforecast Dec 31, 2024