Ecole la Source - Boiler Replacement and Ventilation Upgrades
North Cypress-Langford, Manitoba
Federal contribution
$280,000
Federal share80%
of $350.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 19, 2023
20242025
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of Manitoba
- Construction start
- Sep 29, 2024(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start20 months lateforecast Feb 1, 2023
- Construction end16 months lateforecast Sep 1, 2023
Also in North Cypress-Langford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66896 in the federal list. How to read these figures.