Nova Scotia Mi'kmaw Net Metering Solar
Federal contribution
$3.6M
$3,625,476
Federal share75%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 24, 2026
202420252026
Built
Approved 3.4 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Ulnooweg Development Group
- Construction start
- Mar 4, 2024(actual)
- Construction end
- Mar 30, 2026(actual)
Against the original forecast
- Construction start2 months lateforecast Jan 1, 2024
- Construction end3 months lateforecast Dec 31, 2025