The Greater Shediac Sewerage Commission - WWTP Upgrades (Phase 2)
Federal contribution
$5.8M
$5,815,299
Federal share32%
of $18.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
today
202420252026202720282029
BuiltForecast
Approved 20 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Greater Shediac Sewerage Commission
- Construction start
- Sep 26, 2026(forecast)
- Construction end
- Dec 27, 2028(forecast)
Also in Cap-Acadie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67087 in the federal list. How to read these figures.