RM of Lomond No. 37 - Long Creek Bridge

Lomond No. 37, Saskatchewan

completeHighways and RoadsRNIS
Federal contribution
$166,700
Federal share17%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2024
2024
Built

Approved 10 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 3, 2024(actual)
Construction end
Aug 7, 2024(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 17, 2024

Also in Lomond No. 37

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67117 in the federal list. How to read these figures.