RM of Wheatlands No. 163 - Bridge to Culvert #2
Wheatlands No. 163, Saskatchewan
Federal contribution
$81,083
Federal share17%
of $486.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2024
2024
Built
Approved 10 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- RM of Wheatlands No. 163
- Construction start
- Sep 17, 2024(actual)
- Construction end
- Oct 18, 2024(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Oct 1, 2024
- Construction end2 months earlyforecast Dec 31, 2024
Also in Wheatlands No. 163
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67118 in the federal list. How to read these figures.