RM of Victory No. 226 - Culvert West of NW 10-21-10 W3
Federal contribution
$35,534
Federal share17%
of $213.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2024
2024
Built
Approved 10 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- RM of Victory No. 226
- Construction start
- Jun 1, 2024(actual)
- Construction end
- Oct 22, 2024(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Nov 30, 2024
Also in Victory No. 226
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67119 in the federal list. How to read these figures.