Ulkatcho First Nation - Anahim Lake Solar PV and Energy Storage
Federal contribution
$11.9M
$11,880,750
Federal share75%
of $15.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 19, 2024
202420252026
BuiltForecast
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Ulkatcho Energy Corporation
- Construction start
- Oct 10, 2024(actual)
- Construction end
- Dec 31, 2025(forecast)
Against the original forecast
- Construction start2 months earlyforecast Dec 10, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67149 in the federal list. How to read these figures.