Notre Dame Hospital - Dishroom/Dishwash Exhaust Reconfiguration

Lorne, Manitoba

approvedVentilationCVRIS
Federal contribution
$120,000
Federal share80%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
2023202420252026
BuiltForecast

Approved 2 years before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of Manitoba
Construction start
Feb 15, 2023(forecast)
Construction end
Mar 31, 2026(forecast)