Cumberland House Runway Rehabilitation
Cumberland House, Saskatchewan
Federal contribution
$1.7M
$1,660,000
Federal share50%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2024
today
202420252026202720282029
BuiltForecast
Approved 13 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Saskatchewan Ministry of Highways and Infrastructure
- Construction start
- Oct 1, 2026(forecast)
- Construction end
- Dec 31, 2028(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67253 in the federal list. How to read these figures.