Back to projects

Cumberland House Runway Rehabilitation

Cumberland House, Saskatchewan

approvedRegional And Local AirportsRNIS
Federal contribution
$1.7M
$1,660,000
Federal share50%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2024
today
202420252026202720282029
BuiltForecast

Approved 13 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Oct 1, 2026(forecast)
Construction end
Dec 31, 2028(forecast)