Schedule

Announced and approvedMay 8, 2023
today
20242025202620272028
BuiltForecast

Approved 6 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Jul 1, 2025(actual)
Construction end
Oct 31, 2027(forecast)