Acquisition of 73 electric buses
Federal contribution
$49.1M
$49,060,211
Federal share40%
of $122.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 8, 2023
today
2024202520262027
BuiltForecast
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Réseau de transport de la Capitale (RTC)
- Construction start
- Aug 1, 2026(forecast)
- Construction end
- Mar 31, 2027(forecast)
Also in Québec