Hybrid Electric Bus Purchase (Bow Valley)
Federal contribution
$2.0M
$2,038,510
Federal share40%
of $5.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 19, 2024
today
2024202520262027
BuiltForecast
Approved 9 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Bow Valley Regional Transit Services Commission
- Construction start
- Mar 27, 2024(actual)
- Construction end
- Mar 31, 2027(forecast)
Against the original forecast
- Construction start2 months lateforecast Jan 15, 2024