Tracadie - Principale St. Infrastructures - Phase 2B
Federal contribution
$347,266
Federal share40%
of $868.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 21, 2023
20242025
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Regional Municipality of Tracadie
- Construction start
- May 1, 2023(actual)
- Construction end
- Mar 31, 2025(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 4, 2023
Also in Tracadie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67273 in the federal list. How to read these figures.