Back to projects

Tracadie - Principale St. Infrastructures - Phase 2B

Tracadie, New Brunswick

completeDrinking WaterGIS
Federal contribution
$347,266
Federal share40%

of $868.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 21, 2023
20242025
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 1, 2023(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 4, 2023

Also in Tracadie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67273 in the federal list. How to read these figures.