Milton Watermain Replacement (Phase 3)

George's Brook-Milton, Newfoundland and Labrador

underwayDrinking WaterGIS
Federal contribution
$253,914
Federal share40%

of $634.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
20242025
BuiltForecast

Approved 21 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 2, 2025(actual)
Construction end
Oct 31, 2025(forecast)

Against the original forecast

  • Construction start8 weeks lateforecast May 7, 2025

Also in George's Brook-Milton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67320 in the federal list. How to read these figures.