Back to projects

Station Road Water Extension

Avondale, Newfoundland and Labrador

underwayDrinking WaterGIS
Federal contribution
$405,135
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 5, 2024
202420252026
BuiltForecast

Approved 18 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Avondale
Construction start
Sep 29, 2025(actual)
Construction end
Jan 14, 2026(forecast)

Against the original forecast

  • Construction start4 months lateforecast May 28, 2025

Also in Avondale

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67327 in the federal list. How to read these figures.