Road Intersection Upgrades on Hamilton River Road

Happy Valley-Goose Bay, Newfoundland and Labrador

underwayHighways and RoadsRNIS
Federal contribution
$166,286
Federal share33%

of $498.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2024
today
202420252026
BuiltForecast

Approved 11 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 2, 2025(actual)
Construction end
Oct 26, 2026(forecast)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 6, 2025

Also in Happy Valley-Goose Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67359 in the federal list. How to read these figures.