Water System Improvements
Pool's Cove, Newfoundland and Labrador
Federal contribution
$269,962
Federal share40%
of $674.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
202420252026
BuiltForecast
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of St. Albans
- Construction start
- Apr 22, 2026(forecast)
- Construction end
- Jun 30, 2026(forecast)