RM of Lumsden Wascana Creek Bridge Erosion Protection
Federal contribution
$252,020
Federal share40%
of $630.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2024
today
20252026
BuiltForecast
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Lumsden No. 189, Rural Municipality of Lumsden
- Construction start
- Jul 15, 2026(forecast)
- Construction end
- Oct 31, 2026(forecast)