Town of Leader Potable Water Storage Tank Replacement

Leader, Saskatchewan

completeDrinking WaterGIS
Federal contribution
$750,277
Federal share40%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 24, 2023
20242025
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Leader
Construction start
Apr 1, 2024(actual)
Construction end
May 31, 2025(actual)

Against the original forecast

  • Construction end5 months lateforecast Dec 31, 2024

Also in Leader

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67483 in the federal list. How to read these figures.