Village of Zenon Park Water Storage Rehabilitation
Federal contribution
$80,800
Federal share40%
of $202.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 24, 2023
2024
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Zenon Park
- Construction start
- Apr 30, 2024(actual)
- Construction end
- Oct 29, 2024(actual)
Against the original forecast
- Construction end2 months earlyforecast Dec 31, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67486 in the federal list. How to read these figures.