Back to projects

Palliser Regional Park - Water Treatment Plant Upgrades

Maple Bush No. 224, Saskatchewan

approvedDrinking WaterGIS
Federal contribution
$426,000
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 29, 2024
today
202420252026
BuiltForecast

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Palliser Regional Park
Construction start
Apr 6, 2026(forecast)
Construction end
Sep 30, 2026(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67493 in the federal list. How to read these figures.