Town of Radville - Sewer Main Lining and Manhole Rehabilitation

Radville, Saskatchewan

completeWastewaterGIS
Federal contribution
$374,784
Federal share40%

of $937.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2024
2024
Built

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Radville
Construction start
May 7, 2024(actual)
Construction end
Jun 26, 2024(actual)

Against the original forecast

  • Construction start9 months lateforecast Aug 1, 2023
  • Construction end2 months earlyforecast Aug 30, 2024