Town of Cudworth Sewage Pumping Station Upgrades
Federal contribution
$803,600
Federal share40%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 29, 2024
today
2024202520262027
BuiltForecast
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Cudworth
- Construction start
- Nov 3, 2025(actual)
- Construction end
- Dec 1, 2026(forecast)
Also in Cudworth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67503 in the federal list. How to read these figures.