Village of Glenside Water Plant Upgrade
Federal contribution
$46,000
Federal share40%
of $115.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 29, 2024
2024
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Glenside
- Construction start
- Mar 25, 2024(actual)
- Construction end
- Nov 23, 2024(actual)
Against the original forecast
- Construction start11 months lateforecast May 1, 2023
- Construction end5 weeks earlyforecast Dec 31, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67522 in the federal list. How to read these figures.