Back to projects

RM of Pinto Creek - Kincaid Water Treatment Plant Upgrades

Pinto Creek No. 75, Saskatchewan

approvedDrinking WaterGIS
Federal contribution
$876,024
Federal share40%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 29, 2024
today
20242025202620272028
BuiltForecast

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
RM of Pinto Creek No. 75
Construction start
Mar 31, 2026(forecast)
Construction end
Mar 31, 2028(forecast)

Also in Pinto Creek No. 75

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67524 in the federal list. How to read these figures.