Village of Neudorf Waterline Replacement
Federal contribution
$190,200
Federal share40%
of $475.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 24, 2023
2024
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Neudorf
- Construction start
- May 31, 2024(actual)
- Construction end
- Aug 19, 2024(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2024
- Construction end7 months earlyforecast Mar 31, 2025