Back to projects

Village of Craven Water Supply and Treatment Upgrades

Village of Craven, Saskatchewan

approvedDrinking WaterGIS
Federal contribution
$801,000
Federal share40%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 29, 2024
today
2024202520262027
BuiltForecast

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Craven
Construction start
Jan 5, 2026(forecast)
Construction end
Dec 31, 2026(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67544 in the federal list. How to read these figures.