Village of Neilburg - Water Treatment Plant Upgrades

Neilburg, Saskatchewan

underwayDrinking WaterGIS
Federal contribution
$2.1M
$2,140,672
Federal share40%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 29, 2024
202420252026
BuiltForecast

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Neilburg
Construction start
Apr 24, 2024(actual)
Construction end
Mar 31, 2026(forecast)

Against the original forecast

  • Construction start6 weeks earlyforecast Jun 5, 2024

Also in Neilburg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67545 in the federal list. How to read these figures.