Village of Neilburg - Water Treatment Plant Upgrades
Federal contribution
$2.1M
$2,140,672
Federal share40%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 29, 2024
202420252026
BuiltForecast
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Neilburg
- Construction start
- Apr 24, 2024(actual)
- Construction end
- Mar 31, 2026(forecast)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 5, 2024
Also in Neilburg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67545 in the federal list. How to read these figures.