Back to projects

Raising of the wharf road (Highway 138) in Tête-à-la-Baleine

Côte-Nord-du-Golfe-du-Saint-Laurent, Quebec

approvedDisaster MitigationGIS
Federal contribution
$11.9M
$11,906,500
Federal share54%

of $22.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2026
today
2024202520262027
BuiltForecast

Approved 2.6 years before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 1, 2026(forecast)
Construction end
Oct 12, 2027(forecast)