Back to projects

Island Highway Priority Transit

Colwood, British Columbia

underwayPublic TransitPTIS
Federal contribution
$4.5M
$4,485,684
Federal share40%

of $11.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 27, 2023
today
20242025202620272028
BuiltForecast

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
British Columbia Transit
Construction start
Nov 1, 2023(actual)
Construction end
Nov 1, 2027(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67613 in the federal list. How to read these figures.