Water System Upgrades
Lamaline, Newfoundland and Labrador
Federal contribution
$83,286
Federal share40%
of $208.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
20242025
Built
Approved 18 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Lamaline
- Construction start
- Aug 26, 2024(actual)
- Construction end
- Jan 15, 2025(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 3, 2024
- Construction end7 weeks lateforecast Nov 30, 2024
Also in Lamaline
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67626 in the federal list. How to read these figures.