Lift Station Retrofits

Bonavista, Newfoundland and Labrador

underwayWastewaterGIS
Federal contribution
$369,069
Federal share40%

of $922.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
202420252026
BuiltForecast

Approved 21 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Bonavista
Construction start
Jun 19, 2025(actual)
Construction end
Dec 14, 2025(forecast)

Against the original forecast

  • Construction start3 months lateforecast Mar 25, 2025