Municipality of Grand Lake - Chipman Wastewater Treatment System Replacement
Federal contribution
$7.9M
$7,920,000
Federal share60%
of $13.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 9, 2023
today
20242025202620272028
BuiltForecast
Approved 5 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Grand Lake
- Construction start
- Nov 8, 2024(actual)
- Construction end
- Dec 17, 2027(forecast)
Against the original forecast
- Construction start9 months earlyforecast Jul 28, 2025