Comox Valley - Sewer Conveyance Project - Courtenay Pump Station Replacement

Comox Valley, British Columbia

underwayDisaster MitigationGIS
Federal contribution
$1.3M
$1,346,855
Federal share10%

of $13.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 22, 2024
today
2024202520262027
BuiltForecast

Approved 5 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 21, 2024(actual)
Construction end
Jun 30, 2027(forecast)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 6, 2024