Town of Hepburn - Wastewater Improvements/Expansion
Federal contribution
$1.0M
$1,048,300
Federal share40%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2024
today
20242025202620272028
BuiltForecast
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Hepburn
- Construction start
- May 1, 2026(forecast)
- Construction end
- Mar 31, 2028(forecast)
Also in Hepburn
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67766 in the federal list. How to read these figures.