Village of Daajing Giids Wastewater Treatment Planning and Design
Daajing Giids, British Columbia
Federal contribution
$619,400
Federal share40%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 20, 2023
today
20242025202620272028
BuiltForecast
Approved 7 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Daajing Giids
- Construction start
- Jun 1, 2026(forecast)
- Construction end
- Dec 31, 2027(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67768 in the federal list. How to read these figures.