Tantramar (Dorchester) - Lift Station Upgrades
Federal contribution
$386,880
Federal share40%
of $967.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
20242025
Built
Approved 15 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Tantramar
- Construction start
- Sep 23, 2024(actual)
- Construction end
- Nov 21, 2025(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 31, 2024
Also in Dorchester
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67769 in the federal list. How to read these figures.