Work to protect shorelines against coastal erosion and submersion in the core sector of the municipality of Sainte-Flavie

Sainte-Flavie, Quebec

completeDisaster MitigationGIS
Federal contribution
$5.5M
$5,477,499
Federal share40%

of $13.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 19, 2025
20242025
Built

Approved 16 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jul 4, 2024(actual)
Construction end
Dec 4, 2024(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Aug 15, 2024
  • Construction end4 weeks earlyforecast Dec 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67871 in the federal list. How to read these figures.