Back to projects

Fundy-St. Martins Water System Construction and Wastewater System Design

Fundy-St. Martins, New Brunswick

approvedDrinking WaterRNIS
Federal contribution
$10.9M
$10,860,000
Federal share60%

of $18.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 3, 2025
today
202420252026202720282029
BuiltForecast

Approved 17 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Fundy-St. Martins
Construction start
Apr 1, 2027(forecast)
Construction end
Mar 31, 2029(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67879 in the federal list. How to read these figures.