BC Hydro Customer Connection Project - Westcoast Energy Inc. - Compressor Station CS16
Federal contribution
$15.0M
$15,000,000
Federal share50%
of $30.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2025
202420252026
BuiltForecast
Approved 15 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- British Columbia Hydro and Power Authority
- Construction start
- Apr 7, 2025(actual)
- Construction end
- Apr 30, 2026(forecast)
Against the original forecast
- Construction start8 weeks earlyforecast Jun 1, 2025
Also in Peace River