Belle-Baie - Lift Stations Rehabilitation (Beresford)
Federal contribution
$2.2M
$2,156,400
Federal share60%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 21, 2023
202420252026
BuiltForecast
Approved 2 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Belle-Baie
- Construction start
- Jun 17, 2024(actual)
- Construction end
- Dec 31, 2025(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67916 in the federal list. How to read these figures.