Saskatchewan Health Authority Long-Term Care Facilities HVAC Ventilation Upgrades 2
Federal contribution
$4.1M
$4,073,700
Federal share50%
of $8.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2024
202420252026
Built
Approved 13 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Saskatchewan Health Authority
- Construction start
- Mar 1, 2024(actual)
- Construction end
- Mar 31, 2026(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67925 in the federal list. How to read these figures.