Kwakiutl First Nation - Community Building Energy Retrofits and Solar PV
Kwakiutl First Nation, British Columbia
Federal contribution
$1.5M
$1,544,435
Federal share75%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2024
today
202420252026
BuiltForecast
Approved 10 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Kwakiutl First Nation
- Construction start
- Apr 30, 2026(forecast)
- Construction end
- Aug 31, 2026(forecast)
Also in Kwakiutl First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67930 in the federal list. How to read these figures.