Point May Community Center Retrofit
Point May, Newfoundland and Labrador
Federal contribution
$20,910
Federal share33%
of $62.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
20242025
Built
Approved 20 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Point May
- Construction start
- Jun 15, 2024(actual)
- Construction end
- Nov 7, 2024(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jul 1, 2024
- Construction end3 months lateforecast Jul 31, 2024