Durham Region Replacement of 10 BRT Buses

Durham, Ontario

underwayPublic TransitPTIS
Federal contribution
$3.9M
$3,936,000
Federal share40%

of $9.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2026
202420252026
BuiltForecast

Approved 2.5 years before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Sep 1, 2024(actual)
Construction end
May 31, 2026(forecast)

Against the original forecast

  • Construction start3 months lateforecast Jun 6, 2024