Cove Road Retaining Wall Rehabilitation
Bryant's Cove, Newfoundland and Labrador
Federal contribution
$1.1M
$1,061,908
Federal share80%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 5, 2024
20242025
Built
Approved 19 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Bryant's Cove
- Construction start
- Sep 15, 2023(actual)
- Construction end
- Jul 18, 2025(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2023
- Construction end8 months earlyforecast Mar 31, 2026
Also in Bryant's Cove