Apex Corridor Segment 2-4 Multi-use Pathway Connection, Tsleil-Waututh Nation, Province of British Columbia

Tsleil-Waututh Nation, British Columbia

completeActive TransportationATF
Federal contribution
$3.3M
$3,300,000
Federal share100%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2024
202420252026
Built

Approved 13 months before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Tsleil-Waututh Nation
Construction start
Jul 12, 2024(actual)
Construction end
Feb 27, 2026(actual)

Against the original forecast

  • Construction end4 months lateforecast Oct 31, 2025