7projects·$17.2Mfederal of $36.5M eligible
Hydrogeological groundwater study and new well
$11.8KGarden River First Nation · Drinking Water
underway·approved 2017
Design for Servicing for New Subdivision
$20.0KGarden River First Nation · Drinking Water
complete·approved 2017
Upgrades and Repairs at the Echo River Water treatment plant
$28.5KGarden River First Nation · Drinking Water
underway·approved 2017
Upgrades and Repairs at the Garden River Water Treatment Plant
$41.3KGarden River First Nation · Drinking Water
complete·approved 2017
Transit Viability Assessment for Garden River First Nation, ON
$50.0KGarden River First Nation · Capacity Building
underway·approved 2025
Replacement of Drinking Water Pipes in the Block subdivision in the Village at Garden River First Nation
$2.2MGarden River First Nation · Drinking Water
complete·approved 2021
Huron Central Railway Rehabilitation
$14.9MBlind River +10 · Shortline Rail
complete·approved 2011
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Hydrogeological groundwater study and new well Garden River First Nation | Garden River First Nation | Drinking Water | underway | $11.8K | $23.6K | 2017 |
| Design for Servicing for New Subdivision Garden River First Nation | Garden River First Nation | Drinking Water | complete | $20.0K | $40.0K | 2017 |
| Upgrades and Repairs at the Echo River Water treatment plant Garden River First Nation | Garden River First Nation | Drinking Water | underway | $28.5K | $57.0K | 2017 |
| Upgrades and Repairs at the Garden River Water Treatment Plant Garden River First Nation | Garden River First Nation | Drinking Water | complete | $41.3K | $87.0K | 2017 |
| Transit Viability Assessment for Garden River First Nation, ON Garden River First Nation | Garden River First Nation | Capacity Building | underway | $50.0K | $50.0K | 2025 |
| Replacement of Drinking Water Pipes in the Block subdivision in the Village at Garden River First Nation Garden River First Nation | Garden River First Nation | Drinking Water | complete | $2.2M | $2.9M | 2021 |
| Huron Central Railway Rehabilitation Huron Central Railway Inc. | Blind River +10 more | Shortline Rail | complete | $14.9M | $33.3M | 2011 |