2projects·$268.3Kfederal of $844.5K eligible
Reconstruction pont sur sentier TQ-43
$18.2KSaint-Norbert +1 · Recreation
complete·approved 2015
Program for the renewal of drinking water and wastewater pipes
$250.2KSaint-Norbert-d'Arthabaska · Wastewater
complete·approved 2010
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Reconstruction pont sur sentier TQ-43 Club de Motoneige Carcamp Inc. | Saint-Norbert +1 more | Recreation | complete | $18.2K | $37.3K | 2015 |
| Program for the renewal of drinking water and wastewater pipes Municipality of Saint-Norbert-d'Arthabaska | Saint-Norbert-d'Arthabaska | Wastewater | complete | $250.2K | $807.3K | 2010 |